This template may also be used to develop an Interim Site Management Plan, through which an interim remedial measure or operable unit is monitored, operated and/or maintained before the remedy for the entire site is complete. In this case, the document should be titled and introduced as an interim plan.
Get a QuoteInterim Remedial Measures (IRM) New York State's Inactive Hazardous Waste Disposal Site Remedial Program begins with the discovery of a potential hazardous waste site and follows a path of investigation, remedy selection, design, construction and monitoring. This fact sheet highlights the Interim Remedial Measure (IRM), a remedial action.
Get a Quotethis remedial investigation/interim remedial measures/alternatives analysis (ri/irm/aa) report has been prepared on behalf of 500 seneca street, llc (500 seneca) by benchmark environmental engineering & science, pllc (benchmark) for the 500 seneca street site located in the city of buffalo, new york (site; see figures 1 and 2). 500 seneca elected …
Get a QuoteMeasures Factor Level of Cleanup 1.0 Tine Required 1.0 Minimize Community Impact 0.6 Health, Safety, and Environmental Impacts During Construction 0.7 Technology Status 0.6 Acceptability of Uind .Use Post-Construction 0.4 Risk of Failure 1.1 Compatible with Future Remedial Activities . 0.9 Total Weighted Effectiveness Rating Design and
Get a QuoteThe work was performed in accordance with the MFG, Inc. May 29, 2003 Interim Remedial Measure Work Plan – Limited Excavation (MFG, 2003), which was approved by the RWQCB staff on August 7, 2003. The activities completed through November 2003 were summarized in the Report on Interim Remedial Measures: Source Area Removal (Geomatrix, 2003; herein
Get a QuoteIRM Interim Remedial Measure. Remedial action taken at a contaminated site to reduce the potential for human health or environmental exposure to contaminants at a site before a remedial investigation is complete. ISRA Industrial Site Recovery Act. Pertaining to Industrial Site Recovery Act (ISRA) Rules, pursuant to N.J.A.C. 7:26B.
Get a Quoteinterim remedial measures design report—block e storm drain system page 2-2 concrete pipe (RCP) extending north from MH-4; (2) a 24-inch diameter RCP line extending west from IL-18; and (3) a 15-inch diameter RCP line extending north and east from IL-20.
Get a QuoteThe goal of interim measures (IM) and stabilization is to control or abate imminent threats to human health and the environment from releases at RCRA facilities Interim measures can be implemented at any time during the corrective action process Intent of IM is to be implemented more quickly than traditional remedial measures
Get a QuoteDow undertook a voluntary Interim Remedial Measure in November/December 2000, consisting of the removal and off-site disposal of approximately 2,100 cubic yards of contaminated soil. Where unrestricted use Tier 2 Risk Based Standards for Kansas values could not be reached through excavation because of depth limitations, an infiltration
Get a QuotePROPOSED REMEDIAL MEASURE. The proposed remedy for AOC 20 is No Further Corrective Action Planned (NFCAP) for soils and site-specific groundwater. Excavation activities were performed as Interim Corrective Measures between October 28, 2019 and June 11, 2020.
Get a Quotethe interim measure may prove to be all that is necessary to achieve site remedial goals should all significant threats to human health and the environment be mitigated or eliminated. In terms of timing, an interim measure is generally conducted before the investigation and evaluation of remedial alternatives are completed.
Get a QuoteInterim Measures Various Interim Remedial Measures have been implemented at the Neodesha Refinery Site to address immediate risks and to prevent further off-site migration of the groundwater plume. Based on earlier investigations, wastes were disposed, treated, solidified, and then capped at the north edge of the site.
Get a QuoteOn behalf of PPG Industries, Inc. (PPG), AECOM has prepared this Interim Remedial Measures Work Plan #1 (IRMWP #1) for the Garfield Avenue Site 114, in Jersey City, New Jersey (Site). The location of the Site is shown inFigure 1-1. This IRM Work Plan describes excavation activities designed to remove
Get a QuoteReflect data from Interim Remedial Measures [IRMs] undertaken in Investigative Areas (IAs) 1/4, 2, 6 and 11 West (excavation). - REPORTS: The reports can be found at GW IRM Page: Nov.-Dec. 2017. 4. GROUNDWATER IRM PROGRESS REPORTS/LETTERS - submitted April 2019
Get a QuoteInterim Remedial Measure. Interim Remedial Measure Design Investigation for the 50 Kent Avenue Parcel – February 2013 Interim Remedial Measure Supplemental Pre-Design Investigation Report for the 50 Kent Avenue Parcel – July 2013 Interim Remedial Measure – Design for the 50 Kent Ave Property Holder Area – June 2015
Get a QuoteInterim Remedial Measures - In March 2005, Groendyke Transport submitted a plan for excavation and treatment of contaminated soil from the source area. The excavation was conducted August and September 2006. The excavated soil was treated onsite in a …
Get a Quotepending further soil characterization to determine whether further soil excavation w s required. These actions are consistent with the June, 1992 Interim Remedial Measure Work lan for Soil Clean Up which states "Confirmation soil samples will be retrieved from the bottom and walls of th pit excavation and analyzed for radioactive and chemical
Get a Quotecharacterized in a separate RCRA Facility Investigation (RFI) (Ciba, 1996). An Interim Remedial Measure (IRM) was completed and impacted sedim ent was removed from the former coffer dam area within the river and disposed off -Site in 1996. A sand cap was emplaced at the conclusion of the IRM excavation and has been periodically monitored since
Get a QuoteThis work plan is presented to provide a of work for the completion of scope interim remedial measures (IRMs) during the Remedial Investigation (RI) of the Site, which is currently underway. The IRMs are part of the State Assistance Contract, and this IRM Work Plan has been developed in accordance with NYSDEC Department of
Get a Quotepending further soil characterization to determine whether further soil excavation w s required. These actions are consistent with the June, 1992 Interim Remedial Measure Work lan for Soil Clean Up which states "Confirmation soil samples will be retrieved from the bottom and walls of th pit excavation and analyzed for radioactive and chemical
Get a Quote